Plate 20 of 102ManhattanManhattan Community Board 11
The Beacon: 413 East 120th Street
This site can hold about 325–413 homes under the zoning maximum for qualifying affordable housing. The top of that range is set by the dwelling unit limit (ZR 23-52); qualifying senior housing is exempt from it and could hold up to about 464. The City's LIFT tracker lists 281 homes.
HPD's application and City Planning's 2025 report give about 281 homes plus a superintendent's unit, matching the tracker.
- Index entry
- Tracker status: Post Public Approval
- Lead agency: HPD
Block 1808, lot 8Tax lots from MapPLUTO; street names from the Digital City Map. Pink: this site. Hatched: other City-owned lots. Heavy lines: block edges.
What City documents say
Facts from City documents that bear on the figures below. Each is quoted in the sources, and each speaks as of its document's date.
Occupied Multi-Service Center stays and is enlarged
The lot holds the East Harlem Multi-Service Center, a former public school run by HRA. The approved plan keeps it, rehabilitates it, and adds a sixth floor, for about 50,000 sq ft of community space. The new housing is built on the center's parking lot.
Center housed 12 nonprofits; tenants to move during work
In 2024 the Multi-Service Center hosted 12 nonprofit community organizations. HPD's application says programming will stop during construction and the tenants will be relocated temporarily to nearby East Harlem sites.
2025 approvals: R8 rezoning, MIH area, UDAAP, sale
The City Planning Commission approved the project on January 22, 2025 and the City Council on March 12, 2025: a rezoning from R7-2/R7X to R8 (C 240386 ZMM), a Mandatory Inclusionary Housing area (N 240388 ZRM), and designation and disposition of the site (C 240387 HAM).
Approved plan: about 230,000 sq ft of housing
The approved plan has about 280,000 sq ft of floor area (7.19 FAR): about 230,000 sq ft of housing (5.89 FAR) and about 50,000 sq ft of community facility space (1.30 FAR).
Parts of the site are in the 1% flood zone
Per FEMA's 2015 preliminary flood maps, parts of the project area lie in the 1% annual-chance floodplain and parts in the 0.2% floodplain (2025 Commission report).
Street width from a City document
The City Map change C 240385 MMM, approved in 2025 and filed for recordation on December 31, 2025, narrows East 120th Street from 80 to 60 feet for 363 feet east of First Avenue's east street line, to the east end of the site; the site already extends about 20 feet into the old street. That stretch is now a narrow street. The rest of the block, east of the site, is unchanged and stays a wide street, so the part of the lot within 100 feet of it counts as within 100 feet of a wide street.
What can legally go here
Floor area follows exactly from the Zoning Resolution. Homes are a range, because unit size and building efficiency are choices.
- Lot area
- 39,040 sq ft
- Zoning district
- R8
- Maximum residential floor area
- 235,021–247,459 sq ft39,040 sq ft × 6.02–(0.73 × 6.02 + 0.27 × 7.20) FAR
- With qualifying affordable or senior housing
- 281,088 sq ft39,040 sq ft × 7.20 FAR
- Maximum community facility floor area
- 253,760 sq ft39,040 sq ft × 6.50 FAR
Homes, as a range
| Case | Homes | How |
|---|---|---|
| Low | 328 | 281,088 sq ft × 0.7 ÷ 599 sq ft |
| Base | 406 | 281,088 sq ft × 0.8 ÷ 553 sq ft |
| High | 413 | 281,088 sq ft × 0.85 ÷ 514 sq ft = 464, capped at 281,088 ÷ 680 (ZR 23-52) |
Floor area × efficiency ÷ average home size. Efficiency 0.7–0.85; average home 514–599 sq ft. Assumptions and their basis.
Some figures are shown as a span because the Zoning Resolution sets different limits depending on a condition public data do not settle: whether the site is on a waterfront block, which depends on a case review under ZR 62-11, since the tax block reaches the water's edge.
What binds first
Flood hazard
About 49% of the site (19,700 sq ft) is in FEMA's 2015 Preliminary Flood Insurance Rate Map 1% annual chance floodplain (zone AE). NYC uses this map for flood-resistant construction rules. Flood-resistant construction shapes the ground floor and can reduce usable floor area.
What the neighborhood asked for
Manhattan Community Board 11's formal requests to the City, from its annual Statement of Community District Needs and Budget Requests.
Each quotation below was found word for word on the cited page by script. None reviewed by a person yet.
Housing the board asked for
Provide housing at deeper levels of affordability
“Provide funding for the development of affordable rental and cooperative housing at deeper levels of affordability targeting households living under 30% of AMI.”
FY2027 statement, p. 46 · priority 1 of 4 within the agency · awaiting a person's review
ResponseThe Executive Budget includes a city-wide allocation for this work. Specific locations are determined by the Agency.
Housing for seniors
“Provide funding for the construction of affordable housing for seniors ages 62 and older.”
FY2027 statement, p. 47 · priority 3 of 4 within the agency · awaiting a person's review
ResponseThe Executive Budget includes a city-wide allocation for this work. Specific locations are determined by the Agency.
Other requests in these categories
Expand senior center programming
“East Harlem has a rapidly growing senior population, with over 20% of residents aged 60 and older living below the federal poverty line (NYC Department …”
FY2027 statement, p. 48 · priority 2 of 3 within the agency · awaiting a person's review
ResponseFurther study by the agency of this request is needed.
Extend library hours, expand library programs, and enhance library collections
“Increase funding for NYPL to add resources and staff, and to expand opening hours to 7 days a week. …”
FY2027 statement, p. 60 · priority 1 of 2 within the agency · awaiting a person's review
ResponseRestoring and/or increasing funding is needed for this request. It is recommended that this request be brought to the attention of your elected officials i.e. Borough President and/or City Council Member.
Increase expense funding for libraries
“Increase expense funding for libraries, so branches in every neighborhood can maintain existing levels of service while helping to rebuild a more equitable New York.”
FY2027 statement, p. 60 · priority 2 of 2 within the agency · awaiting a person's review
ResponseRestoring and/or increasing funding is needed for this request. It is recommended that this request be brought to the attention of your elected officials i.e. Borough President and/or City Council Member.
3 other requests in these categories are listed on the web page.
What gets in the way
Flags are flags, not verdicts. Each comes from a public layer, named in the sources.
- Hazard
In the 1% annual chance floodplain (2015 preliminary map)
About 49% of the site (19,700 sq ft) is in FEMA's 2015 Preliminary Flood Insurance Rate Map 1% annual chance floodplain (zone AE). NYC uses this map for flood-resistant construction rules.
- Hazard
In the 1% annual chance floodplain (effective 2007 map)
About 78% of the site (31,400 sq ft) is in the 1% annual chance floodplain on FEMA's effective 2007 Flood Insurance Rate Map, which flood insurance still uses (MapPLUTO flags it too).
- Hazard
Stormwater flooding in an extreme storm (2080s)
DEP's Stormwater Flood Map (extreme stormwater flood with 2080 sea level rise) shows flooding on about 17% of the site (6,700 sq ft), nearly all of it nuisance flooding (4 in to 1 ft).
- Caution
Floor area depends on a condition public data do not settle
The Zoning Resolution sets different limits depending on a condition that public data do not settle here, so some figures are shown as a span. The note under the floor area figures says which condition, and why.
- Caution
The lot has a building on it
The lot has a building on record with 80,095 sq ft of gross building area, completed around 1954 (MapPLUTO; gross area includes space zoning does not count). Zoning counts floor area already on a lot toward its maximum, so the figures above are the most the land could hold in total, not what could be added while that building stands.
- Note
Partly in a Mandatory Inclusionary Housing area
About 83% of the site is inside DCP's mapped Mandatory Inclusionary Housing area, where MIH option 2 applies: new housing on that part must include permanently affordable homes (ZR 27-131). The rest of the site is outside it.
Nearest subway station: 125 St (4 5 6), 0.5 mi in a straight line.
What this doesn't account for
Public data and the zoning text answer the questions above. These need information that is not public, or a decision that belongs to the City.
- Public land use review (ULURP). Selling or leasing City land, or approving a housing project on it, generally goes through ULURP (community board, borough president, City Planning Commission, City Council), and this estimate does not presume the outcome.
- Disposition of City property (Charter 384 / UDAAP). Transferring the land needs Mayoral approval under Charter Sec. 384 and, for HPD projects, usually Urban Development Action Area designation and project approval under NY General Municipal Law Article 16.
- Environmental review (CEQR/SEQRA). Any discretionary approval, disposition or City funding triggers CEQR/SEQRA review, which can require mitigation (e.g. for hazardous materials, noise or historic resources) or reshape the project.
- (E) designations. A lot with an (E) designation or environmental restrictive declaration for hazardous materials, air quality or noise cannot receive building permits until the Office of Environmental Remediation signs off.
- Subsurface and site conditions. Unknown soil, rock, groundwater and contamination can shrink or eliminate cellars and add foundation and cleanup costs, and HPD requires every project to investigate and, if needed, remediate contamination.
- Deed restrictions and reverter clauses. Land the City bought or sold may carry deed restrictions or reverter clauses limiting its use, which must be checked in title records (ACRIS) and DCAS's deed-restriction database.
- Parkland alienation. If a site is municipal parkland, it cannot be sold or used for housing without an act of the State Legislature signed by the Governor.
- Current occupants, uses and agency plans. Many City-owned lots are in active use or assigned to an agency, or have funded capital projects, and this estimate does not reflect relocation needs or agency plans (check COLP and the Capital Commitment Plan).
- Mapped streets, easements and utilities. Mapped-but-unbuilt ('paper') streets, sewer and water easements and utility lines can take land out of the buildable area, and no permit may be issued for a building in the bed of a mapped street.
- Street access. A lot with no frontage on a mapped street cannot get a building permit on its own and must be combined with a neighboring lot or have access mapped.
- Landmarks review. Sites that are individual landmarks or inside historic districts need Landmarks Preservation Commission approval, which can limit demolition, height and bulk.
- Flood-resistant construction. Sites in the 1% annual chance floodplain (or the 0.2% shaded X-Zone for critical facilities) must meet Building Code Appendix G, whose elevation and floodproofing rules can cost usable ground-floor and cellar space.
- Airport height limits. Near JFK, LaGuardia and Floyd Bennett Field, zoning flight-obstruction surfaces cap building height, and tall structures anywhere need FAA notice.
- State and federal funding conditions. Federal or State money brings its own requirements (e.g. HUD environmental review under 24 CFR Part 58, Davis-Bacon prevailing wages, Section 3 hiring) that can change cost, timing and program.
- Zoning capacity is a ceiling, not a plan. The figures show what zoning allows, and actual HPD projects often build less, for example to fit neighborhood context, a community facility or funding limits.
Checks
What has been verified on this page, and by what.
- Tax lots (1)
- 1-01808-0008Confirmed against City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)
- Lot and zoning records compared with DCP's live data
- Agrees
- Figures reproduced by a separate calculation
- Agrees
- Notes
- On September 25, 2026, the MapPLUTO records and zoning district map behind this page were compared with DCP's live MapPLUTO (26v2) and zoning district layers for its lot; every compared field and district boundary matched. A separate calculation, written from the method page and run on the same downloaded City data on September 25, 2026, reproduced the lot area (39,040 sq ft), the zoning portions, the floor area (standard 235,021–247,459; with qualifying affordable or senior housing 281,088; community facility 253,760 sq ft), the homes (low 328, base 406, high 413), and the flags and what limits the site first.
Sources
Superscript numbers next to figures refer to this list. Select one to see the source.
- LIFT Tracker (Land Inventory Fast Track)Dataset · NYC Mayor's Office · as of July 30, 2026 · retrieved September 23, 2026
- City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)Document · NYC City Planning Commission · as of January 22, 2025
- HPD land use application 2022M0328, LR Item 3 Project Description: The Beacon, 413 East 120th Street (revised 2024-08-30)Document · NYC Department of Housing Preservation and Development (filed on DCP's Zoning Application Portal, project 2022M0328, Notice of Certification package) · as of August 30, 2024
- City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendmentDocument · NYC City Planning Commission · as of January 22, 2025
- City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)Document · NYC City Planning Commission · as of January 22, 2025
- HPD land use application 2022M0328, LR Item 3 Project Description: The Beacon, 413 East 120th Street (revised 2024-08-30)Document · NYC Department of Housing Preservation and Development (filed on DCP's Zoning Application Portal, project 2022M0328, Notice of Certification package) · as of August 30, 2024
- DCP transmittal for filing and recordation, ULURP No. C 240385 MMM (Map ACC No. 30274)Document · NYC Department of City Planning (Map Filing Materials, ZAP project 2023M0160) · as of December 31, 2025
- ZAP project record 2022M0328 (The Beacon: C 240386 ZMM, C 240387 HAM, N 240388 ZRM)Document · NYC Department of City Planning, Zoning Application Portal · as of September 25, 2026
- City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)Document · NYC City Planning Commission · as of January 22, 2025
- City Planning Commission report C 240385 MMM (City Map change, East 120th Street between First and Pleasant Avenues)Document · NYC Department of City Planning · as of January 22, 2025
- City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendmentDocument · NYC City Planning Commission · as of January 22, 2025
- City Planning Commission report C 240385 MMM (City Map change, East 120th Street between First and Pleasant Avenues)Document · NYC City Planning Commission · as of January 22, 2025
- City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendmentDocument · NYC City Planning Commission · as of January 22, 2025
- DCP memorandum to the Office of the City Register: block and lot numbers for ULURP mapping action C 240385 MMM (Map ACC No. 30274) filed for recordationDocument · NYC Department of City Planning (Map Filing Materials, ZAP project 2023M0160) · as of December 31, 2025
- MapPLUTODataset · NYC Department of City Planning · as of September 9, 2026 · retrieved September 25, 2026
- Zoning Resolution § 23-22Zoning Resolution · NYC Department of City Planning · as of September 10, 2026
- Zoning Resolution § 23-22Zoning Resolution · NYC Department of City Planning · as of September 10, 2026
- Zoning Resolution § 62-322Zoning Resolution · NYC Department of City Planning · as of September 10, 2026
- Zoning Resolution § 23-22Zoning Resolution · NYC Department of City Planning · as of September 10, 2026
- Zoning Resolution § 24-11Zoning Resolution · NYC Department of City Planning · as of September 10, 2026
- Declared assumption: building efficiencyDeclared assumption · as of September 23, 2026
- Declared assumption: average home size (net)Declared assumption · as of September 23, 2026
- Zoning Resolution § 23-52Zoning Resolution · NYC Department of City Planning
- FEMA 2015 Preliminary Flood Insurance Rate Map (flood hazard zones)Dataset · FEMA, via NYC Department of City Planning · as of March 16, 2026 · retrieved September 25, 2026
- 2022 NYC Building Code, Appendix G (Flood-Resistant Construction)Document · NYC Department of Buildings
- FEMA 2015 Preliminary Flood Insurance Rate Map: area of each lot in each zoneDataset · FEMA, via NYC Department of City Planning · as of March 16, 2026 · retrieved September 25, 2026
- FEMA 2007 effective Flood Insurance Rate Map: area of each lot in each zoneDataset · FEMA, via NYC Department of City Planning · as of March 16, 2026 · retrieved September 25, 2026
- NYC Stormwater Flood Map: Extreme stormwater flood with 2080 sea level riseDataset · NYC Department of Environmental Protection, via NYC Department of City Planning · as of September 8, 2025 · retrieved September 25, 2026
- NYC Stormwater Flood Map: Extreme stormwater flood with 2080 sea level rise: area of each lot in each categoryDataset · NYC Department of Environmental Protection, via NYC Department of City Planning · as of September 8, 2025 · retrieved September 25, 2026
- Mandatory Inclusionary Housing areasDataset · NYC Department of City Planning · as of September 9, 2026 · retrieved September 25, 2026
- Zoning Resolution rules packZoning Resolution · Public Ground, from the NYC Zoning Resolution
- FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11Document · NYC Department of City Planning · retrieved September 23, 2026
- FY2027 Register of Community Board Budget Requests (Adopted Budget), Manhattan Community Board 11Document · NYC Office of Management and Budget · as of June 30, 2026
- FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11Document · NYC Department of City Planning · retrieved September 23, 2026
- FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11Document · NYC Department of City Planning · retrieved September 23, 2026
- FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11Document · NYC Department of City Planning · retrieved September 23, 2026
- MTA Subway StationsDataset · Metropolitan Transportation Authority · as of September 25, 2026 · retrieved September 25, 2026
- Digital City Map street centerlinesDataset · NYC Department of City Planning · as of December 1, 2025 · retrieved September 25, 2026
- New York City Charter Sec. 197-c (Uniform land use review procedure)Document
- NYC Charter Sec. 384 (Disposal of property of the city)Document
- CEQR Technical Manual, Chapter 2 (December 2025 edition)Document
- Zoning Resolution 11-15 (Environmental Requirements)Document
- HPD Design Guidelines for New Construction 2026Document
- Deed Restriction Database (NYC Open Data rfu7-paqe)Document
- Handbook on the Alienation and Conversion of Municipal Parkland (NYS OPRHP, revised 2017-09-01)Document
- City Owned and Leased Property (COLP), NYC Open Data fn4k-qyk2Document
- NY General City Law Sec. 35Document
- NY General City Law Sec. 36Document
- LPC - Applications pageDocument
- 2022 NYC Building Code, Appendix G (as amended by Local Law 77 of 2023)Document
- Zoning Resolution 61-21 (Restriction on Highest Projection of Building or Structure)Document
- HPD ELLA Term Sheet (updated 2020-03-10)Document
- CPC report C 260071 HAM (1727 Amsterdam Avenue)Document
- Zoning districts (NYZD)Dataset · NYC Department of City Planning · as of August 17, 2026 · retrieved September 25, 2026
1. LIFT Tracker (Land Inventory Fast Track)
- Where
- ArcGIS layer LIFT_Tracker/FeatureServer/0
- As of
- July 30, 2026
- Retrieved
- September 23, 2026
One point per project. BBLs resolved by point-in-lot against MapPLUTO, HPD's Local Law 125 report, or address geocoding; see the method page.
2. City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)
- Where
- PDF page 1, item 1(a). Retrieved 2026-09-25. The report's header and resolution print 'January 22, 2024'; the Commission vote was January 22, 2025 (ZAP milestones; DCP map transmittal).
- As of
- January 22, 2025
the designation of property located at 413 East 120th Street (Block 1808, Lot 8, and an approximately 7,260 square foot area of current East 120th Street running south of Lot 7501 (Condo Lots 1001-1003 (and Lot 8 for approximately 363 feet)) as an Urban Development Action Area
3. HPD land use application 2022M0328, LR Item 3 Project Description: The Beacon, 413 East 120th Street (revised 2024-08-30)
- Where
- PDF page 1, section I.
- As of
- August 30, 2024
a new 21-story development containing approximately 281 units of affordable housing plus one superintendent's unit
4. City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendment
- Where
- p.3, Background
- As of
- January 22, 2025
The proposed development would include 281 income-restricted housing units (IRHUs) and renovated and enlarged community facility space at the existing East Harlem MSC
5. City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)
- Where
- PDF page 6, 'Proposed Development'. Retrieved 2026-09-25. The report's header and resolution print 'January 22, 2024'; the Commission vote was January 22, 2025 (ZAP milestones; DCP map transmittal).
- As of
- January 22, 2025
The Proposed Development would contain approximately 280,000 square feet of total floor area (7.19 FAR), including approximately 230,000 square feet of residential floor area (5.89 FAR) and approximately 50,000 square feet of community facility floor area (1.30 FAR). | The residential building of the Proposed Development will be an infill development on the HRA MSC parking lot
6. HPD land use application 2022M0328, LR Item 3 Project Description: The Beacon, 413 East 120th Street (revised 2024-08-30)
- Where
- PDF page 4, section V.
- As of
- August 30, 2024
The Development Site contains an existing five-story building that houses the HRA MSC, which hosts 12 not-for-profit community organizations. | During the development process, programming at the MSC will be halted to facilitate the Proposed Development, including rehabilitation of the MSC building, and the existing tenants will be temporarily relocated to nearby East Harlem sites.
7. DCP transmittal for filing and recordation, ULURP No. C 240385 MMM (Map ACC No. 30274)
- Where
- single page
- As of
- December 31, 2025
duly approved by the City Planning Commission on January 22, 2025 (Calendar Number 24) and subsequently approved by the City Council on March 12, 2025 (Resolution 0803-2025), which action comprised final approval.
8. ZAP project record 2022M0328 (The Beacon: C 240386 ZMM, C 240387 HAM, N 240388 ZRM)
- Where
- project attributes, actions and milestones (dataset record): City Council Review ended 2025-03-12, outcome 'Adopted' (retrieved 2026-09-25)
- As of
- September 25, 2026
Record excerpt"dcp-projectname":"The Beacon","dcp-publicstatus":"Completed" ... "dcp-ulurpnumber":"C240386ZMM" ... "dcp-ulurpnumber":"C240387HAM" ... "dcp-ulurpnumber":"N240388ZRM" ... "dcp-actualenddate":"2025-03-12T04:00:00.000Z","statuscode":"Completed","dcp-milestonesequence":58
9. City Planning Commission report C 240387 HAM (The Beacon: UDAAP designation, project approval and disposition, 413 East 120th Street)
- Where
- PDF page 5, 'Surrounding Area'. Retrieved 2026-09-25. The report's header and resolution print 'January 22, 2024'; the Commission vote was January 22, 2025 (ZAP milestones; DCP map transmittal).
- As of
- January 22, 2025
portions of the Project Area are located within the 1% annual chance (100-year) floodplain and the 0.2% annual chance (500-year) floodplain.
10. City Planning Commission report C 240385 MMM (City Map change, East 120th Street between First and Pleasant Avenues)
- Where
- p.5, description of the area discontinued and closed
- As of
- January 22, 2025
Starting at the point of intersection of the easterly line of 1st Avenue and the northerly line of East 120th Street, discontinued and closed: 1. Thence, running 363.00 feet in an easterly direction along the northerly line of East 120th Street, discontinued and closed; 2. Thence, running 20.00 feet in a southerly direction
11. City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendment
- Where
- p.9, 'City Map Change (C 240385 MMM)'
- As of
- January 22, 2025
HPD requests a City Map amendment to eliminate, discontinue and close the northern portion of the mapped street at East 120th Street from the eastern streetline of First Avenue to the easternmost boundary at the end of the Development Site (approximately 363 feet east of First Avenue), and to reestablish the street line 20 feet to the south.
12. City Planning Commission report C 240385 MMM (City Map change, East 120th Street between First and Pleasant Avenues)
- Where
- p.1. The report's header prints 'January 22, 2024'; the Commission vote was January 22, 2025 (DCP map transmittal).
- As of
- January 22, 2025
This action would facilitate the demapping the norther portion of East 120th Street extending 363 feet east from First Avenue, reducing the width of the mapped street from 80 to 60 feet
13. City Planning Commission report C 240387 HAM (The Beacon, 413 East 120th Street): City Map amendment
- Where
- p.9, Background. The report's header prints 'January 22, 2024'; the Commission vote was January 22, 2025 (DCP map transmittal).
- As of
- January 22, 2025
The Development Site currently extends beyond the mapped street line of East 120th Street by approximately 20 feet, and, by extension, the frontage of the existing MSC building extends into the mapped street line by approximately 11 feet. ... The proposed mapped width of East 120th Street in this area would be reduced from 80 feet to 60 feet.
14. DCP memorandum to the Office of the City Register: block and lot numbers for ULURP mapping action C 240385 MMM (Map ACC No. 30274) filed for recordation
- Where
- single page
- As of
- December 31, 2025
Block & lot numbers for the ULURP mapping action(s) filed for recordation on December 31, 2025 | Record Map ACC No. 30274 (For ULURP No. C 240385 MMM) against the following tax lot(s):
15. MapPLUTO 26v2
- As of
- September 9, 2026
- Retrieved
- September 25, 2026
16. Zoning Resolution § 23-22
- Where
- R8; Not within 100 ft of a wide street: 6.02 FAR
- As of
- September 10, 2026
R8A R8X R8 | 6.02 | 7.20
17. Zoning Resolution § 23-22
- Where
- R8; Within 100 ft of a wide street: 7.20 FAR
- As of
- September 10, 2026
R8 | 7.20¹ | 8.64² ... ¹ For zoning lots, or portions thereof, located within 100 feet of a wide street
18. Zoning Resolution § 62-322
- Where
- R8; Waterfront block (ZR 62-322): within-100-ft-of-wide-street provision does not apply: 6.02 FAR
- As of
- September 10, 2026
However, for districts without a letter suffix, the regulations applicable to portions of a zoning lot within 100 feet of a wide street shall not apply.
19. Zoning Resolution § 23-22
- Where
- R8, qualifying affordable housing or qualifying senior housing; All qualifying affordable/senior housing, in MIH areas whatever the street, except UAP developments or qualifying senior housing within 100 ft of a wide street outside MIH areas (8.64): 7.20 FAR
- As of
- September 10, 2026
R8A R8X R8 | 6.02 | 7.20
20. Zoning Resolution § 24-11
- Where
- R8: 6.50 FAR
- As of
- September 10, 2026
R8 | 6.50 | 75 | 65
21. Declared assumption: building efficiency
- Where
- low 0.7, base 0.8, high 0.85
- As of
- September 23, 2026
Net home area as a share of residential floor area. Basis: 2025 HCR Design Guidelines, PDF p. 40, Sec. 3.4.1a 'Overall Building Efficiency', Table 3.4.1; 2025 HCR Design Guidelines, PDF p. 40, Sec. 3.4.1; Market & Financial Study: NYC Mandatory Inclusionary Housing (BAE Urban Economics, BJH Advisors, James Lima Planning + Development), PDF p. 68 (printed p. 64), Appendix C, Table C-1 'Developer Interview Summary'; Market & Financial Study: NYC Mandatory Inclusionary Housing, PDF p. 41 (printed p. 37), 'Zoning and Floor Area Ratio'; HPD Design Guidelines for New Construction 2026, PDF p. 28, 'Unit Area Calculation'. A declared assumption; no City agency publishes this ratio.
22. Declared assumption: average home size (net)
- Where
- low 514, base 553, high 599 sq ft
- As of
- September 23, 2026
HPD target net areas by bedroom count, weighted by HPD's observed bedroom mix. Basis: HPD Design Guidelines for New Construction 2026, PDF p. 31, Sec. 4.4.1; HPD Design Guidelines for New Construction 2026, PDF p. 33, Sec. 4.5.1; HPD Design Guidelines for New Construction 2026, PDF p. 36, Sec. 4.6.1; HPD Design Guidelines for New Construction 2026, PDF p. 39, Sec. 4.7.1; HPD Design Guidelines for New Construction 2026, PDF p. 42, Sec. 4.8.1; HPD Design Guidelines for New Construction 2026, PDF p. 6, 'Applicability'; HPD Design Guidelines for New Construction, Version 2.02 (edition in force before 2026-10-01), PDF pp. 42-58 (e.g. p. 44 for 0-BR, p. 58 for 4-BR), Secs. 5.3-5.8 tables 'TARGET NET'; HPD ELLA Term Sheet (Extremely Low & Low-Income Affordability), PDF p. 5, 'Design and Construction Requirements'; Affordable Housing Production by Building (NYC Open Data hg8x-zxpr), fields studio_units, _1_br_units ... _6_br_units; filter reporting_construction_type='New Construction' AND all_counted_units >= total_units - 1.
23. Zoning Resolution § 23-52
- Where
- Dwelling unit factor 680
In the districts indicated, for buildings containing multiple dwelling residences, the maximum number of dwelling units permitted shall be determined by dividing the maximum residential floor area permitted on the zoning lot by the applicable dwelling unit factor. ... For all other types of multiple dwelling residences, the applicable dwelling unit factor shall be 680. Fractions equal to or greater than three-quarters resulting from this calculation shall be considered to be one dwelling unit.
24. FEMA 2015 Preliminary Flood Insurance Rate Map (flood hazard zones) 360497_20150130
- As of
- March 16, 2026
- Retrieved
- September 25, 2026
25. 2022 NYC Building Code, Appendix G (Flood-Resistant Construction)
- Where
- § G102.2
Uses FEMA's 2015 Preliminary FIRMs for flood hazard areas, and the higher of the 2007 or 2015 maps for elevations.
26. FEMA 2015 Preliminary Flood Insurance Rate Map: area of each lot in each zone 360497_20150130
- As of
- March 16, 2026
- Retrieved
- September 25, 2026
27. FEMA 2007 effective Flood Insurance Rate Map: area of each lot in each zone
- As of
- March 16, 2026
- Retrieved
- September 25, 2026
28. NYC Stormwater Flood Map: Extreme stormwater flood with 2080 sea level rise
- As of
- September 8, 2025
- Retrieved
- September 25, 2026
29. NYC Stormwater Flood Map: Extreme stormwater flood with 2080 sea level rise: area of each lot in each category
- As of
- September 8, 2025
- Retrieved
- September 25, 2026
30. Mandatory Inclusionary Housing areas 202607
- As of
- September 9, 2026
- Retrieved
- September 25, 2026
31. Zoning Resolution rules pack
- Where
- 248 districts, every value cited to a ZR section
ZR text: ZR site home page: "All text changes approved by the city council as of Sep 10, 2026". Every Article II section cited here (21-14, 23-xx, 24-xx, 27-xx) and 62-32x, 74-79, 75-24, 75-42x shows "Last Amended 12/5/2024" (City of Yes for Housing Opportunity, N 240290 ZRY); exceptions among cited sections: 11-122 (8/14/2025, Midtown South Mixed-Use Plan), 11-25 (6/29/1994), 12-10 page (3/26/2026), 62-361 (7/16/2026); no citywide (ZRY) text amendment has been adopted since (Recently Adopted list, 12/5/2024-9/10/2026, contains only site-specific and neighborhood amendments). 12-10 "wide street" last amended 3/26/2026 (Allen Street Mall, N 250307 ZRM - adds Allen Street roadways in Manhattan CD 3).
32. FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11 FY2027
- Where
- PDF p. 46
- Retrieved
- September 23, 2026
33. FY2027 Register of Community Board Budget Requests (Adopted Budget), Manhattan Community Board 11 FY2027 Adopted
- Where
- Agency response
- As of
- June 30, 2026
34. FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11 FY2027
- Where
- PDF p. 47
- Retrieved
- September 23, 2026
35. FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11 FY2027
- Where
- PDF p. 48
- Retrieved
- September 23, 2026
36. FY2027 Statement of Community District Needs and Community Board Budget Requests, Manhattan Community Board 11 FY2027
- Where
- PDF p. 60
- Retrieved
- September 23, 2026
37. MTA Subway Stations
- As of
- September 25, 2026
- Retrieved
- September 25, 2026
38. Digital City Map street centerlines
- As of
- December 1, 2025
- Retrieved
- September 25, 2026
39. New York City Charter Sec. 197-c (Uniform land use review procedure)
- Where
- Sec. 197-c(a)(8) and (a)(10)
(8) Housing and urban renewal plans and projects pursuant to city, state and federal housing laws; ... (10) Sale, lease (other than the lease of office space), exchange, or other disposition of the real property of the city
40. NYC Charter Sec. 384 (Disposal of property of the city)
- Where
- Sec. 384(a)
No real property of the city may be sold, leased, exchanged or otherwise disposed of except with the approval of the mayor and as may be provided by law unless such power is expressly vested by law in another agency.
41. CEQR Technical Manual, Chapter 2 (December 2025 edition)
- Where
- PDF p. 1 (printed p. 2-1)
CEQR requires all city agencies to determine whether discretionary actions they directly approve, fund, or undertake may significantly and adversely affect the environment.
42. Zoning Resolution 11-15 (Environmental Requirements)
- Where
- ZR 11-15(a); last amended 2012-03-28
Prior to issuing a building permit or temporary or final certificate of occupancy ... on a tax lot that has an (E) designation or an environmental restrictive declaration related to hazardous materials, noise or air quality, the Department of Buildings (DOB) shall be furnished with a notice issued by OER stating that OER does not object
43. HPD Design Guidelines for New Construction 2026
- Where
- PDF p. 13, Secs. 1.1.1 and 1.1.4
1.1.1 Avoid excessive excavation. Particularly in areas with unknown subsurface conditions, and where rock or high-water tables are prevalent, proposed cellars may have to be reduced, relocated, or even eliminated.
44. Deed Restriction Database (NYC Open Data rfu7-paqe)
- Where
- dataset description
A searchable electronic database of all real property upon which a deed restriction was imposed by the Department of Citywide Administrative Services, pursuant to Local Law 176 of 2016.
45. Handbook on the Alienation and Conversion of Municipal Parkland (NYS OPRHP, revised 2017-09-01)
- Where
- PDF p. 3, 'Parkland Alienation'
In order to convey parkland away, or to use parkland for another purpose, a municipality must receive prior authorization from the State in the form of legislation enacted by the New York State Legislature and approved by the Governor.
46. City Owned and Leased Property (COLP), NYC Open Data fn4k-qyk2
- Where
- dataset description (version 20260430)
City Owned and Leased Properties (COLP) is published by the Department of City Planning (DCP) as required by chapter 204 of the City Charter. It includes the location and current use of all City-owned and leased properties.
47. NY General City Law Sec. 35
- Where
- GCL 35
For the purpose of preserving the integrity of such official map or plan no permit shall hereafter be issued for any building in the bed of any street or highway shown or laid out on such map or plan
48. NY General City Law Sec. 36
- Where
- GCL 36
No permit for the erection of any building shall be issued unless a street or highway giving access to such proposed structure has been duly placed on the official map or plan
49. LPC - Applications page
- Where
- page text
The Landmarks Preservation Commission (LPC) helps preserve the City's designated landmark properties by regulating changes made to these buildings and sites.
50. 2022 NYC Building Code, Appendix G (as amended by Local Law 77 of 2023)
- Where
- PDF p. 1, Sec. G102.1
This appendix, in conjunction with the New York City Construction Codes, provides minimum requirements for development located, in whole or in part, in special flood hazard areas and shaded X-Zones within the jurisdiction of New York City
51. Zoning Resolution 61-21 (Restriction on Highest Projection of Building or Structure)
- Where
- ZR 61-21; 61-11 designates JFK, LaGuardia and U.S. Naval Air Station (Floyd Bennett Field)
the highest projection of any building or other structure hereafter constructed ... shall not penetrate: (a) the approach surfaces, the transitional surfaces, the horizontal surface, or the conical surface, whichever is more restrictive, within the Airport Approach District of the flight obstruction area
52. HPD ELLA Term Sheet (updated 2020-03-10)
- Where
- PDF p. 4
Projects funded with Federal funds require compliance with Section 3 new hires and Davis Bacon prevailing wages, as applicable.
53. CPC report C 260071 HAM (1727 Amsterdam Avenue)
- Where
- PDF p. 8
while CHO increased the maximum floor area permitted on the project site, the project sponsor does not intend to take advantage of the additional floor area.
54. Zoning districts (NYZD)
- As of
- August 17, 2026
- Retrieved
- September 25, 2026